Skip to main content
← All research

Part 8 of 11

Canada's Data Centre Race → see all chapters

Jobs and Economics: The Per-Megawatt Reckoning

July 20, 2026

CS
Colin Smillie

Founder, Developer, AI Researcher

The short version.A data centre is a construction project with a small permanent staff bolted on. The build creates a real, temporary boom, and the finished site adds to the local property-tax base. But the ongoing payroll is thin. The honest way to compare is jobs per megawatt, because megawatts are the scarce input every project fights over. On that measure data centres deliver roughly 0.2 to 0.35 permanent jobs per MW, while an EV battery plant delivers 25 to 40 times more jobs per MW, and steel and petrochemical complexes more still. Meta’s CA$13 billion, 1 gigawatt Alberta build lands at about 300 permanent jobs.

Two numbers, and only one of them lasts

Every data-centre announcement comes with a jobs figure, and almost every one of them is really two figures blended into a headline. The first is construction employment, which is large, temporary, and gone the moment the concrete cures. The second is permanent operations employment, which is what the community actually keeps. Reporting them as one number is where the jobs story goes wrong.

Meta’s Sturgeon County project is the cleanest illustration in our data. The company projects roughly 3,000 construction jobs during the build and about 300 permanent jobs once the 1 gigawatt facility is running. That is a ten-to-one collapse. The construction crews frame the ribbon-cutting; the 300 operators keep the lights on for the next twenty years. Both numbers are worth having, but only if you keep them apart, and only if you remember they are projections in a company newsroom post, not realized payroll.

Hold on to that word, projections. Nearly every employment figure in this chapter, for data centres and for the alternatives alike, comes from an announcement or an economic-impact statement written by a party with a reason to make the number large. We treat them as plans, not headcounts.

Jobs per megawatt, benchmarked

Raw job totals are unfair comparisons, because a bigger project should employ more people. The question worth asking is how much employment you get per unit of the one input everyone is competing for: grid power. Megawatts are scarce, they are shared, and in Alberta they are rationed. So jobs per megawatt is the metric that actually decides whether a given slice of the grid was well spent.

Here is where the comparison lands, drawn from our project data. The data-centre figure is an industry staffing benchmark rather than a measured Canadian facility, so treat it as a rule of thumb that Meta’s own numbers happen to confirm:

  • Hyperscale data centre: about 0.2 to 0.35 permanent jobs per MW. At 380 MW that is roughly 75 to 130 permanent staff; at 100 MW, about 20 to 35. Meta’s 1 GW Sturgeon build sits right in the band at 0.3 (about 300 permanent).
  • EV battery cell plant: Volkswagen PowerCo in St. Thomas, Ontario draws a dedicated 380 MW line to support about 3,000 permanent jobs, roughly 8 jobs per MW, or 25 to 40 times the data-centre rate for the same power.
  • Steel (electric-arc furnace): Algoma Steel in Sault Ste. Marie runs a roughly 2,800-person integrated steelworks on about 110 to 115 MW of self-generation. That headline is total workforce rather than net-new hires, but the per-MW employment still dwarfs a data centre at the same load.
  • Petrochemicals: Dow’s Path2Zero complex in Fort Saskatchewan projects 400 to 500 permanent plus 7,000 to 8,000 construction jobs. Its grid draw is not disclosed, so we cannot compute a clean per-MW figure, but the employment scale is an order of magnitude above a data centre.
  • For context, non-industrial uses: the Toronto Port Lands housing plan turns former industrial land into about 5,000 homes and roughly 2,900 jobs while drawing very little dedicated power, and the Port of Montreal’s Contrecoeur terminal projects 1,200 operational jobs plus up to 8,000 during construction.

The pattern is consistent and it is not close. A megawatt routed to a battery plant, a steel mill, or a port employs far more people than a megawatt routed to a data centre. That does not make data centres worthless, but it does puncture the idea that they are jobs engines. They are not. They are capital-intensive infrastructure that happens to need a modest crew to run.

The capital-per-job problem

The weakness sharpens when you put the money next to the payroll. Data centres are expensive per megawatt: our capital data puts Meta Sturgeon at roughly CA$13 million per MW, QScale in Quebec at about CA$7.4 million, eStruxture’s Calgary build at CA$8.3 million, Beacon’s Alberta campuses near CA$10 million, and Vantage’s Quebec City site at CA$15.6 million. That capital buys chips, cooling, and power, not staff.

Divide the spend by the permanent jobs and the ratio is stark. Meta’s CA$13 billion facility, at about 300 permanent jobs, works out to roughly CA$43 million of capital per permanent job. Volkswagen’s St. Thomas battery plant, at about CA$7 billion for around 3,000 jobs, is closer to CA$2.3 million per job. On capital-per-permanent-job, the battery plant is nearly twenty times more labour-efficient. Both figures come straight from the announced totals, and both should be read as planning numbers, but the direction is unambiguous.

The tax base we mostly cannot see

If the jobs case is weak, the honest counter is the tax case. A large data centre is a durable, high-assessed-value property that pays municipal and provincial taxes for decades, and unlike a battery plant it does not need thousands of workers, houses, or schools to support it. In principle that is the real economic argument for welcoming one.

In practice, we cannot verify it, and that is a finding in itself. Across the Canadian projects we track, tax-base-per-megawatt is essentially undisclosed. The alternative-land-use dataset carries an explicit tax-base column, and for every project in it, that field is empty. The single concrete economic-return figure anywhere in our records is Meta’s estimate of about CA$250 million a year to Alberta from the Sturgeon build, and even that number blends taxes with broader economic activity rather than isolating property tax. So the strongest argument for data centres is also the least documented one. Anyone claiming a data centre pays for itself in tax revenue is, on the public record, asking to be taken on faith.

What the incentives actually buy

Follow the incentives and the difference in kind becomes clear. The alternatives in our data were pulled in with cash: Honda’s Ontario EV hub was offered up to CA$5 billion in government support, Umicore’s battery-materials plant about CA$1 billion, Dow’s petrochemical complex roughly CA$1.8 billion in provincial incentive-program support, and Air Products’ hydrogen complex about CA$461 million. Those subsidies were explicitly tied to manufacturing jobs and supply-chain anchoring.

The data centres in our data mostly did not get cash. What they got was regulatory acceleration and power-siting advantage. For most projects the government-incentive field reads “no cash subsidy disclosed.” What stands out instead is Alberta scrapping the provincial environmental impact assessment for Kevin O’Leary’s Wonder Valley in April 2026, and Premier Smith citing the abeyance of federal Clean Electricity Regulations as part of the backdrop to Meta’s build. The public gives data centres speed and clearance rather than dollars. That is a cheaper deal for the treasury, but it also means the province is spending its regulatory and clean-power capital rather than getting paid for it, and getting few permanent jobs in return.

When a data centre is, and is not, a good deal

None of this makes data centres a bad idea everywhere. There is a version of the trade that is clearly worth it: a facility that lands on brownfield land nobody else wants, connects without displacing higher-value load from the grid, pays a well-documented property-tax stream, and anchors a sovereign-AI capability the country actually needs. On stranded power or genuinely surplus capacity, 300 permanent jobs plus a tax base plus strategic compute is a fine outcome.

The deal turns bad when the ingredients are scarce. When a data centre takes one of only two Phase-1 grid connections Alberta will issue before 2028, or draws down finite hydro that a battery plant or a steel mill could have used to employ twenty-five times as many people, the opportunity cost is real and large. That is the case the next chapters take up: the capital flowing into this build, and the alternative uses the same land, power, and money could have served.

A caveat cuts both ways here. The high-employment alternatives are not guaranteed either. Northvolt’s 3,000-job Quebec gigafactory went bankrupt in 2025, and Honda’s Ontario hub was shelved in 2026 amid soft EV demand. Their job numbers were projections too, and some of those projections evaporated. The point is not that batteries always beat data centres. It is that when you compare on jobs per megawatt, honestly and with the construction and permanent numbers kept separate, the data centre is close to the bottom of the list.

The takeaway

Data centres are sold as economic development, and the label is only half right. The construction boom is real but temporary. The tax base may be real but is almost never disclosed in a way anyone can check. The permanent employment is small, on the order of 0.2 to 0.35 jobs per megawatt, and Meta’s flagship 1 gigawatt project confirms it at about 300 jobs. Measured against the batteries, steel, and petrochemicals competing for the same scarce power, that is tens of times fewer jobs for each megawatt spent, 25 to 40 times against an EV battery plant and more against steel. The right way to greet a data-centre announcement is not to ask how many jobs, but how many permanent jobs per megawatt, and then to ask what else that megawatt could have done.

Frequently asked questions

How many permanent jobs does a data centre actually create?

Fewer than most announcements suggest, once you separate one-time construction from ongoing operations. The industry benchmark is roughly 0.2 to 0.35 permanent jobs per megawatt, so a 100 MW facility supports on the order of 20 to 35 permanent staff, and a 380 MW hyperscale site about 75 to 130. Meta's 1 GW Sturgeon County build is projected at about 300 permanent jobs against 3,000 during construction. These operating figures are projections, not realized headcount.

What is the difference between construction jobs and permanent jobs?

Construction jobs are one-time and temporary, lasting the two to four years of the build, after which they end. Permanent jobs are the ongoing operations staff who run the facility. Meta Sturgeon illustrates the split clearly: about 3,000 construction jobs collapse to about 300 permanent once the site is running, a ten-to-one ratio. Announcements tend to lead with the larger construction number.

Why is jobs per megawatt the honest metric?

Because megawatts are the scarce, shared input every large project competes for, so comparing employment per MW shows what a given slice of grid capacity actually buys. On that measure data centres look weak: about 0.2 to 0.35 permanent jobs per MW, against roughly 8 for an EV battery plant like Volkswagen's St. Thomas site and well over 20 for an electric-arc steelworks like Algoma. That is roughly 25 to 40 times more per MW than a data centre for the battery plant, and higher still for the steelworks.

How much tax revenue does a data centre generate?

Our dataset cannot answer this precisely, and that gap is itself a finding. Tax-base-per-MW figures are essentially undisclosed across the Canadian projects we track. The one concrete number is Meta's estimate of about CA$250 million a year to Alberta from its Sturgeon County build, and even that blends taxes with broader economic activity. Property-tax base is the real economic case for a data centre, but it is rarely published in a way that allows a per-MW comparison.

Are the job numbers in announcements reliable?

Treat them as projections, not realized employment. They come from company and municipal economic-impact statements, which have every incentive to lead with the largest plausible figure, usually the construction total. Several of the high-employment alternatives in our comparison, including Northvolt in Quebec and Honda in Alliston, were themselves announced with large job counts and then cancelled or shelved, a reminder that an announced number is a plan, not a payroll.

Sources

Primary and reputable secondary sources: Meta Data Centers and Global News (the Sturgeon County build, its construction and permanent job projections, and the CA$250 million annual figure); Volkswagen Group and Hydro One (the St. Thomas PowerCo battery plant and its 380 MW line); Algoma Steel and Northern Ontario Business (the electric-arc furnace conversion); Dow and CBC News (the Path2Zero petrochemical complex); Waterfront Toronto and CreateTO (the Port Lands housing plan); the Canada Infrastructure Bank and the Prime Minister’s Office (Contrecoeur); QScale, eStruxture, Vantage Data Centers, and Beacon AI Centers (per-megawatt capital costs); the Government of Canada, CBC News, and Electrek (the Honda, Umicore, Dow, and Air Products incentive figures); and National Observer (the Wonder Valley environmental-assessment exemption). Job and tax figures are announcement projections unless otherwise noted, and tax-base-per-megawatt is largely undisclosed across the dataset.